Whilst the airport is still being affected by restrictions due to Covid, we have moved ever so slightly further forward with the fuel installation. The civil works have been completed and we now await the specialist equipment for connection. The installation of emergency controls including fire alarm and extinguishers followed by filling, testing and certification. I am still unable to give a definitive date but optimistic that we may have fuel for April.
I will update again when I get more news on the progress.
Thank you for your patience.
Station Manager.